FICTIONAL TRAINING DEMO. Use only the supplied source text below; do not search work files, email, calendars or the web. Produce drafts only. Turn these supplied project meeting notes into an action register with task, explicitly named owner, stated deadline, dependency and evidence excerpt. Mark missing owners or dates as unassigned or not stated. Separate decisions from suggestions. Finish with the three clarifications needed before sending a status update. SOURCE TEXT PROJECT MEETING NOTES — FICTIONAL P1: Launch target September 30. Mina will deliver the draft guide September 18. P2: Website QA must finish before launch; owner and due date were not assigned. P3: Jo suggested adding a webinar. No decision was made. P4: Omar will confirm product screenshots by September 21. Mina needs those screenshots for the final guide.